Successful Clusters....  
ABB Faridabad Cluster - Faridabad |
Ten supplier companies of ABB Faridabad have reported astounding achievements after the successful closure of the CII-Cluster programme on 26th June 2007. At the closure all ten companies shared their success stories after undergoing a 12 months programme on adopting best manufacturing practices. The cluster accrued tremendous benefits and reported improvement in Inventory Turnover Ratio (76%), achieving delivery schedule up to 95%. This programme has helped companies to reduce accident frequency (77%), accident severity (57%) customer complaint and rejection by 57% and machine breakdown hours and frequency by 20%.
Benefits - CII ABB Supplier Cluster
Sr. No. |
Key Indicator |
UOM |
Before |
After |
Improvement
in % |
1 |
Financial Benefits |
In Crores |
0 |
1.13 |
|
2 |
Benefits in Space Saving |
Sq. Ft |
NA |
8040 |
|
3 |
Floor Space Utilization |
Rs./Sq. Mtrs |
11733 |
15543 |
32 |
4 |
Accident Frequency Rate |
PPM |
2029 |
449 |
77 |
5 |
Accident Severity Rate |
PPM |
3813 |
1676 |
56 |
6 |
Inventory Turn Over |
No. |
14 |
24 |
76 |
7 |
Customer Complaints |
No. |
7 |
3 |
57 |
8 |
Customer Return |
PPM |
5834 |
3654 |
37 |
9 |
In Process Rejection |
PPM |
8595 |
5975 |
30 |
10 |
VAPCO |
Ratio |
3 |
4 |
39 |
11 |
Delivery Schedule Adherence |
% |
84 |
95 |
13 |
12 |
Absenteeism |
& |
10 |
7 |
30 |
13 |
Labour Productivity |
Unit / Hrs |
44 |
48 |
9 |
14 |
Machine Break Down Hrs |
Nos. |
1052 |
873 |
17 |
15 |
Machine Break Down Frequency |
Nos. |
27 |
22 |
19 |
16 |
5S Score |
% |
28 |
60 |
|
17 |
Employee Involvement |
% |
3 |
53 |
|
18 |
3M Identified / Eliminated |
Nos. |
0 |
383 |
|